Parking Lot Improvements
Project Location | Pillar Point Harbor |
---|---|
Status: | COMPLETED |
Estimated Completion: | Spring 2023 |
Description: | Slurry & stripe parking Lots B, C1, and C3. Include additional crosswalks, and install EV stations. |
Justification: | Maintenance on parking lots will extend the life of the asphalt, added crosswalks will improve pedestrian safety, and EV stations will provide a public service & support climate friendly traffic. |
Strategic Goal/Operating Impact: | 1) Comprehensive Long-Rang Planning Guides District Actions and Decision-Making. |
2) Infrastructure Improvements are Guided by Comprehensive Long-Term Planning. | |
3) Environmental Stewardship |
PPH C-1, C-2, C-3 and Launch Ramp Access Road Paving/Resurfacing Project, 2022-05: Initiated September 2022
Invitation for Bid solicited, bids opened 11/29/22, low bid approved by Board on December 21, 2022. NTP will be issued in the spring, after CDP is obtained.