In preparation for the construction work starting at the marina this summer, we are providing our Waterside Logistics Plan for your reference. The approximate timeline for this work is as follows:
Phase 1A  July 2020 - August 2020
Phase 1B  August 2020 - December 2020
Phase 2    December 2020 - May 2021

Contains image of Oyster Point Marina
Phase 1A  July 2020 - August 2020
Construction phasing plan showing temporary parking, dock access changes, and public meeting info. Designated dates included.
Phase 1B  August 2020 - December 2020
Contains image of Oyster Point Marina
Phase 2    December 2020 - May 2021