Kilroy Oyster Point Redevelopment (Update)
February 11, 2020
To Members of the Oyster Point Marina Community,
In preparation for the construction work starting at the marina this summer, we are providing our Waterside Logistics Plan for your reference (see sidebar for images). The approximate timeline for this work is as follows:
Phase 1A July 2020 - August 2020
Phase 1B August 2020 - December 2020
Phase 2 December 2020 - May 2021
We welcome any questions or comments you may have.
Sincerely,
Kilroy Oyster Point Development Team
Oyster Point Hotline
(415) 808-6030
oysterpointhotline@kilroyrealty.com
January 24, 2020
Additional trucking is expected along Oyster Point Boulevard between US-101 off-ramp and Marina Boulevard from material delivery to site on a daily basis (Monday through Friday) until end of February, between the hours of 12:00 a.m. and 7:00 a.m.
Noise Alert:
Pile-driving operations continue through February, 2020. The contractor is installing approximately 1,500 piles. Work is scheduled Monday through Friday, between 8:00 a.m. and 5:00 p.m.
For questions or more information, please contact the Oyster Point Hotline at 415.808.6030 or email oysterpointhotline@kilroyrealty.com.
October 25, 2019
KILROY OYSTER POINT REDEVELOPMENT PROJECT (379 Oyster Point Blvd.)
Additional trucking is expected along Oyster Point Boulevard between US-101 off-ramp and Marina Boulevard from material delivery to site on a daily basis (Monday through Friday) until Wednesday, November 20, between the hours of 12:00 a.m. and 7:00 a.m. Commuters can expect delays and are encouraged to use alternate routes.
Underground utility work scheduled at the intersection of Oyster Point Boulevard and Gull Drive through Monday, October 28. Work will impact travel in the eastbound and westbound directions along Oyster Point Boulevard as it will be reduced to a single travel lane in each direction between 8:00 p.m. and 5:00 a.m. Work will occur Monday through Friday. Commuters can expect delays and are encouraged to use alternate routes. Please follow signage and safety personnel instructions at all times
Noise Alert:
Pile-driving operations continue through January, 2020. The contractor expects to install approximately 1,500 piles. Work is scheduled Monday through Friday, between 8:00 a.m. and 5:00 p.m.
For questions or more information, please contact the Oyster Point Hotline at 415.808.6030 or email oysterpointhotline@kilroyrealty.com.
October 11, 2019
Additional trucking is expected along Oyster Point Boulevard between US-101 off-ramp and Marina Boulevard from material delivery to site on a daily basis (Monday through Friday) until Wednesday, November 20, between the hours of 12:00 a.m. and 7:00 a.m. Commuters can expect delays and are encouraged to use alternate routes.
Underground utility work scheduled at the intersection of Oyster Point Boulevard and Gull Drive through Friday, October 25. Work will impact travel in the eastbound and westbound directions along Oyster Point Boulevard as it will be reduced to a single travel lane in each direction between 8:00 p.m. and 5:00 a.m. Work will occur Monday through Friday. Commuters can expect delays and are encouraged to use alternate routes. Please follow signage and safety personnel instructions at all times
Noise Alert:
Pile-driving operations continue through January, 2020. The contractor expects to install approximately 1,500 piles. Work is scheduled Monday through Friday, between 8:00 a.m. and 5:00 p.m.
Public Outreach Meeting:
On Thursday, October 17, 2019 @ 5:30 PM, interested parties are invited to join the Kilroy Oyster Point Team for their monthly public outreach meeting. The meeting is at 384 Oyster Point Blvd, Suite #1, South San Francisco. Please RSVP to oysterpointhotline@kilroyrealty.com
For questions or more information, please contact the Oyster Point Hotline at 415.808.6030 or email oysterpointhotline@kilroyrealty.com.
October 4, 2019
KILROY OYSTER POINT REDEVELOPMENT PROJECT (379 Oyster Point Blvd.)
Additional trucking is expected along Oyster Point Boulevard between US-101 off-ramp and Marina Boulevard from material delivery to site on a daily basis (Monday through Friday) until Wednesday, November 20, between the hours of 12:00 a.m. and 7:00 a.m. Commuters can expect delays and are encouraged to use alternate routes.
Underground utility work scheduled at the intersection of Oyster Point Boulevard and Gull Drive will start on Sunday, October 6. Work will impact travel in the eastbound and westbound directions along Oyster Point Boulevard as it will be reduced to a single travel lane in each direction between 8:00 p.m. and 5:00 a.m. Work will occur Monday through Friday. Commuters can expect delays and are encouraged to use alternate routes. Please follow signage and safety personnel instructions at all times
Noise Alert:
Pile-driving operations continue through January, 2020. The contractor expects to install approximately 1,500 piles. Work is scheduled Monday through Friday, between 8:00 a.m. and 5:00 p.m.
For questions or more information, please contact the Oyster Point Hotline at 415.808.6030 or email oysterpointhotline@kilroyrealty.com.
September 18, 2019 Update
Contractor efforts continue on pile installation. Excavation, cutting of piles, and reinforcing for pile caps are underway. Material deliveries continue through January, 2020. Work for temporary power for the project from Gull Drive is underway.
Update: Scheduled Power Outages
To Members of the Oyster Point Marina Community:
Please note that the power outages will affect different marinas on each day. On Tuesday, October 1st, the work will take place in the West Basin. On Wednesday, October 2nd the work will take place in the East Basin. Below you may find the scheduled activities for each day:
October 1st, 7 am - 9 pm (West Basin)
- De-energize (0.5 hrs.)
- Relocate Gear to new pad (3 hrs.)
- Pull Wire for feeder/service (0.5 hrs.)
- Cutover on Piers (10 hrs.)
October 2nd, 10 am - 1 pm (East Basin)
- De-energize (0.5 hrs.)
- Pull feeder/service and make connections (2 hrs.)
- Energize (0.5 hrs.)
We and Teichert Construction welcome any comments you may have regarding this work and thank you for your patience during this time. We regret not including the locations in our first notice.
Sincerely,
Kilroy Oyster Point Development Team
Oyster Point Hotline
(415) 808-6030
oysterpointhotline@kilroyrealty.com
Teichert Construction
John Bridges
(925) 750-4582
jbridges@teichert.com
September 16, 2019
Message from Kilroy Oyster Point
Notice: Scheduled Power Outages
Teichert Construction has scheduled power outages occurring on Tuesday, October 1st and Wednesday, October 2nd. Below you may find the scheduled activities for each day:
October 1st, 7 am - 9 pm
- De-energize (0.5 hrs.)
- Relocate Gear to new pad (3 hrs.)
- Pull Wire for feeder/service (0.5 hrs.)
- Cutover on Piers (10 hrs.)
October 2nd, 10 am - 1 pm
- De-energize (0.5 hrs.)
- Pull feeder/service and make connections (2 hrs.)
- Energize (0.5 hrs.)
We and Teichert Construction welcome any comments you may have regarding this work and thank you for your patience during this time.
Sincerely,
Kilroy Oyster Point Development Team
Oyster Point Hotline
(415) 808-6030
oysterpointhotline@kilroyrealty.com
Teichert Construction
John Bridges
(925) 750-4582
jbridges@teichert.com
8/9/2019
Alert:
Additional trucking is expected for material delivery to the site on a daily basis (Monday through Friday) until Wednesday, November 20 between
12:00 a.m. and 7:00 a.m. Additional trucking is expected along Oyster Point Boulevard between US-101 off-ramp and Marina Boulevard. Commuters can expect delays and are encouraged to use alternate routes.
Noise Alert:
Pile driving operations continue through January 2020. The contractor expects to install approximately 1,500 piles. Work is scheduled Monday through Friday between 8:00 a.m. and 5:00 p.m.
Public Outreach Meeting:
On Thursday, August 15, 2019 @ 5:30 PM, interested parties are invited to join the Kilroy Oyster Point Team for their monthly public outreach meeting. The meeting will be held at 384 Oyster Point Blvd, Suite #1, South San Francisco. Please RSVP to oysterpointhotline@kilroyrealty.com
For questions or more information, contact the Oyster Point Hotline at (415) 808-6030 or email oysterpointhotline@kilroyrealty.com
7/19/2019
Project Update:
Contractor efforts continue on forming and pouring for elevator pits and mat slab foundation. Material deliveries continue for the pile driving operations that will continue through January, 2020. Work for temporary power for the project from Gull Drive is underway.
Alert:
Additional trucking is expected for material delivery to the site on a daily basis (Monday through Friday) until Wednesday, November 20 between
12:00 a.m. and 7:00 a.m. Additional trucking is expected along Oyster Point Boulevard between US-101 off-ramp and Marina Boulevard. Commuters can expect delays and are encouraged to use alternate routes.
Hathaway Dinwiddie will be making a 1,880 yd. concrete pour on Saturday, July 27th. Set up for this work will begin at 4 a.m. The pouring will begin at 5 a.m. with anticipated completion by 3:30 p.m. Additional updates will be provided, should any changes to this schedule become necessary.
We welcome any comments you may have regarding this work, and thank you for your patience during this time.
Kilroy Oyster Point Development Team
Oyster Point Hotline
(415) 808-6030
oysterpointhotline@kilroyrealty.com
7/5/2019 Update
A concrete pour is scheduled for Saturday, July 27 starting at 4:00 a.m. - 8:00 p.m. Additional trucking is expected as trucks enter and exit the site along Oyster Point Boulevard just north of Marina Boulevard.
Additional trucking is expected for material delivery to the site on a daily basis (Monday through Friday) until Wednesday, November 20, 2019, between the hours of 12:00 a.m. and 7:00 a.m. Additional trucking expected along Oyster Point Boulevard between US-101 off-ramp and Marina Boulevard. Commuters can expect delays and are encouraged to use alternate routes.
Noise Alert:
Pile driving operations continue through January 2020. The contractor expects to install approximately 1,500 piles. Work is scheduled Monday through Friday between 8:00 a.m. and 5:00 p.m.
For questions or more information, please contact the Oyster Point Hotline at (415) 808-6030 or email oysterpointhotline@kilroyrealty.com.
6/7/2019
Additional trucking is expected for material delivery to the site on a daily basis (Monday - Friday) until Wednesday, November 20 between the hours of 12:00 a.m. - 7:00 a.m. Additional trucks are expected along Oyster Point Boulevard between US-101 off-ramp and Marina Boulevard. Commuters may expect delays and are encouraged to use alternate routes.
5/2/2019 NOTICE: COMMENCEMENT OF PILE DRIVING
To Members of the Oyster Point Marina Community:
We are pleased to inform you that construction has officially started on our Phase 1 building at Kilroy Oyster Point.
This new phase will initiate pile driving activities (hammering of a steel tube into the ground) beginning on Monday, May 6th and will continue through January 2020. The contractor anticipates installing approximately 1,500 piles for the project at a rate of approximately 8 to 17 piles per day. To reduce disruptions to residents and businesses, work will be performed during normal business hours (8 a.m. to 5 p.m.), Monday – Friday. Additional updates will be provided, should any changes to this schedule become necessary.
We welcome any comments you may have regarding this work, and thank you for your patience during this time.
Sincerely,
Kilroy Oyster Point Development Team
Oyster Point Hotline
(415) 808-6030
oysterpointhotline@kilroyrealty.com